Definitions for "Replanning"
change in the original plan for accomplishing authorize contractual requirements. There are two type s of replan ning effort: Internal Replanning change in the original plan that remains within the scope of the authorize contract, cause d by a need to compensate for cost, schedule, or technical problem s which have made the original plan unrealistic; External Replan ning - Customer-directed changes to the contract in the form of a change order that calls for a modification in the original plan. [D04653] QWF Action s performed for any remaining effort within project scope. Often the cost and/or schedule variance s are zeroed out at this time for history items. [D01631] WST APM
The redistribution of budget for future work. Traceability is required to previous baselines and attention to funding requirements needs to be considered in any replanning effort.